Nepal: Small Towns Water Supply and Sanitation Sector
Project Details
-
Project Officer
Xiaoyan Ye
South Asia Department
Request for information -
Country/Economy
Nepal
Related Projects
Project Name | Small Towns Water Supply and Sanitation Sector | ||||
Project Number | 31402-013 | ||||
Country / Economy | Nepal |
||||
Project Status | Closed | ||||
Project Type / Modality of Assistance | Loan |
||||
Source of Funding / Amount |
|
||||
Strategic Agendas | Environmentally sustainable growth |
||||
Drivers of Change | Governance and capacity development |
||||
Sector / Subsector | Agriculture, natural resources and rural development / Rural water policy, institutional and capacity development - Rural water supply services |
||||
Gender Equity and Mainstreaming | |||||
Description | |||||
Project Rationale and Linkage to Country/Regional Strategy | |||||
Impact |
Project Outcome | |
---|---|
Description of Outcome | |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location |
Safeguard Categories | |
---|---|
Environment | B |
Involuntary Resettlement | |
Indigenous Peoples |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Responsible ADB Officer | Xiaoyan Ye |
Responsible ADB Department | South Asia Department |
Responsible ADB Division | Nepal Resident Mission |
Executing Agencies |
Ministry of Physical Infrastructure and Transport Mr. P. P. Kadaria [email protected] Ministry of Physical Planning and Works, Singhadurbar |
Timetable | |
---|---|
Concept Clearance | 15 Jun 1997 |
Fact Finding | 21 Feb 2000 to 07 Mar 2000 |
MRM | 29 Mar 2000 |
Approval | 12 Sep 2000 |
Last Review Mission | - |
PDS Creation Date | 20 Nov 2006 |
Last PDS Update | 16 Jul 2009 |
Loan 1755-NEP
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
12 Sep 2000 | 18 Dec 2000 | 16 Mar 2001 | 31 Dec 2006 | 30 Nov 2008 | 03 Dec 2009 |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 53.90 | Cumulative Contract Awards | |||
ADB | 35.00 | 17 Jun 2022 | 32.13 | 0.00 | 100% |
Counterpart | 18.90 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 17 Jun 2022 | 32.13 | 0.00 | 100% |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Small Towns Water Supply and Sanitation Sector Project | Project/Program Completion Reports | Sep 2010 |
Small Towns Water Supply and Sanitation Sector Project | Reports and Recommendations of the President | Aug 2000 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
Title | Document Type | Document Date |
---|---|---|
Nepal: Small Towns Water Supply and Sanitation Sector Project | Validations of Project Completion Reports | Dec 2012 |
Related Publications
Title | Document Type | Document Date |
---|---|---|
Tapping the Unreached: Nepal Small Towns Water Supply and Sanitation Sector Projects─A Sustainable Model of Service Delivery | Guides | Sep 2017 |
Nepal: Small Towns Water Supply and Sanitation Project | Papers and Briefs | Sep 2011 |
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
-
Results Reality Virtual Exhibit Trailer
ADB’s virtual Results Reality website provides a glimpse of the results of completed and ongoing water sector projects in Nepal. -
Nepal Water and Sanitation: Local Action Shows Results
Communities in towns that line Nepal’s main highways are better able to deal with the severe water and sanitation issues that result from sudden and massive urbanization. -
In Nepal, 'Good Water Changes Everything'
A small town water supply and sanitation sector project in Nepal is empowering the Tharu minority and keeps students in school.
Tenders
No tenders for this project were found.
Contracts Awarded
No contracts awarded for this project were found
Procurement Plan
None currently available.