Papua New Guinea: Urban Water Supply and Sanitation Project
Project Details
-
Project Officer
Alexandra L. Conroy
Pacific Department
Request for information -
Country/Economy
Papua New Guinea -
Sector
- Water and other urban infrastructure and services
Project Name | Urban Water Supply and Sanitation Project | ||||
Project Number | 52226-001 | ||||
Country / Economy | Papua New Guinea |
||||
Project Status | Proposed | ||||
Project Type / Modality of Assistance | Grant Loan |
||||
Source of Funding / Amount |
|
||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||
Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development Partnerships |
||||
Sector / Subsector | Water and other urban infrastructure and services / Urban sanitation - Urban sewerage - Urban water supply |
||||
Gender Equity and Mainstreaming | Gender equity | ||||
Description | |||||
Project Rationale and Linkage to Country/Regional Strategy | |||||
Impact | Incidence of waterborne disease in provincial towns is reduced (Medium Term Development Plan 2 2016 2017)a | ||||
Outcome | Access to safe water and sanitation in provincial urban areas increased. | ||||
Outputs | Urban water infrastructure constructed. Urban sanitation infrastructure constructed. Awareness of hygiene and hygiene behaviors improved. Institutional and project management capacity is enhanced. |
||||
Geographical Location | Nation-wide, Port Moresby |
Safeguard Categories | |
---|---|
Environment | B |
Involuntary Resettlement | B |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Responsible ADB Officer | Alexandra L. Conroy |
Responsible ADB Department | Pacific Department |
Responsible ADB Division | PAUW |
Executing Agencies |
Department of National Planning & Monitoring Vulupindi Haus, P.O. Box 631 Waigani, NCD, Port Moresby Papua New Guinea |
Timetable | |
---|---|
Concept Clearance | 21 Sep 2018 |
Fact Finding | 21 Jul 2019 to 27 Jul 2019 |
MRM | 24 Jan 2020 |
Approval | - |
Last Review Mission | - |
Last PDS Update | 03 Oct 2018 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Urban Water Supply and Sanitation Project: Initial Poverty and Social Analysis | Initial Poverty and Social Analysis | Sep 2018 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
No tenders for this project were found.
Contracts Awarded
No contracts awarded for this project were found
Procurement Plan
None currently available.