Project Name | e-Government Development and Infrastructure Project | ||||
Project Number | 55338-001 | ||||
Country / Economy | Timor-Leste |
||||
Project Status | Proposed | ||||
Project Type / Modality of Assistance | Loan |
||||
Source of Funding / Amount |
|
||||
Strategic Agendas | Inclusive economic growth |
||||
Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development |
||||
Sector / Subsector |
Information and communication technology / ICT strategy and policy, and capacity development Public sector management / Public administration |
||||
Gender Equity and Mainstreaming | Effective gender mainstreaming | ||||
Description | |||||
Project Rationale and Linkage to Country/Regional Strategy | |||||
Impact | E-government developed to support cohesive government and service delivery (Timor-Leste Strategic Development Plan, 20112030) |
||||
Outcome | Efficiency of, and citizens' participation in, e-government services improved |
||||
Outputs | National data center and disaster recovery facilities established E-government network connectivity enhanced Digital service capacities of the government strengthened |
||||
Geographical Location | Nation-wide |
Safeguard Categories | |
---|---|
Environment | C |
Involuntary Resettlement | C |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Responsible ADB Officer | Chongvilaivan, Aekapol |
Responsible ADB Department | Southeast Asia Department |
Responsible ADB Division | Public Management, Financial Sector and Trade Division, SERD |
Executing Agencies |
Council for Administration of the Infrastructure Fund |
Timetable | |
---|---|
Concept Clearance | 24 Mar 2022 |
Fact Finding | 02 Oct 2023 to 20 Oct 2023 |
MRM | 19 Jan 2024 |
Approval | - |
Last Review Mission | - |
Last PDS Update | 24 Mar 2022 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
e-Government Development and Infrastructure Project: Initial Poverty and Social Analysis | Initial Poverty and Social Analysis | Mar 2022 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.