SPF-2022-18-01-0138 |
Pakistan: Supporting Public–Private Partnership Investments in Sindh Province |
- Environment
- Involuntary resettlement
- Climate change
- Stakeholder engagement
|
- Complaint received, 9 November 2022
- Complaint acknowledged and registered, 11 November 2022
- Eligibility (eligible), 20 December 2022
|
SPF-2022-16-02-0136 |
Pakistan: Punjab Intermediate Cities Improvement Investment Project |
- Land acquisition, compensation, and valuation
- Lack of meaningful consultation and participation
- Dissatisfaction on the problem-solving process at the project-level
|
- Complaint received, 17 October 2022
- Complaint acknowledged and registered, 20 October 2022
- Eligibility (eligible), 15 November 2022
|
SPF-2022-13-03-0133 |
Georgia: Batumi Bypass Road Project |
|
- Complaint received, 25 August 2022
- Complaint acknowledged and registered, 26 August 2022
- Eligibility (not eligible, complainants have yet to address problem with concerned ADB operations department), 16 September 2022
|
SPF-2022-09-02-0129 |
Pakistan: Balakot Hydropower Development Project |
- Land acquisition
- Compensation
- Valuation
|
- Complaint received, 28 June 2022
- Complaint acknowledged and registered, 30 June 2022
- Eligibility (not eligible, complainants have yet to address problem with concerned ADB operations department), 19 July 2022
|
SPF-2022-07-01-0127 |
Pakistan: Balakot Hydropower Development Project |
- Land acquisition
- Compensation
- Valuation
|
- Complaint received, 21 June 2022
- Complaint acknowledged and registered, 23 June 2022
- Eligibility (not eligible, complainants have yet to address problem with concerned ADB operations department), 19 July 2022
|
SPF-2022-04-0124 |
Pakistan: Khyber Pakhtunkhwa Provincial Roads Improvement Project (Additional Financing) |
- Dust pollution
- Road safety issues
- Impacts on residential areas and agricultural lands
- Flooding
|
- Complaint received, 12 May 2022
- Complaint acknowledged and registered, 12 May 2022
- Eligibility (not eligible, complainants have yet to address problem with concerned ADB operations department), 9 June 2022
|
SPF-2022-01-01-0121 |
Pakistan: Jalalpur Irrigation Project
Pakistan: Greater Thal Canal Irrigation Project |
- Environment and infrastructure issues
|
- Complaint received, 1 February 2022
- Complaint acknowledged and registered, 2 February 2022
- Eligibility (not eligible, complainants have yet to address problem with concerned ADB operations department), 15 February 2022
|
SPF-2021-17-03-0120 |
Pakistan: Jalalpur Irrigation Project |
- Negative impacts to residential area
- Alignment of the canal
|
- Complaint received, 29 November 2021
- Complaint acknowledged and registered, 1 December 2021
- Eligibility (not eligible, complainants have yet to address problem with concerned ADB operations department), 15 December 2021
|
SPF-2021-16-01-0119 |
Pakistan: Khyber Pakhtunkhwa Cities Improvement Project |
- Negative impacts to ecotourism, irrigation, and crop production
- Water quality Water quality
- Lack of information and consultation
|
- Complaint received, 19 November 2021
- Complaint acknowledged and registered, 19 November 2021
- Eligibility (not eligible, complainants have yet to address problem with concerned ADB operations department), 16 December 2021
- Closed, 14 July 2022
|
SPF-2021-15-02-0118 |
Pakistan: Flood Emergency Reconstruction and Resilience Project |
- Adverse impacts on the existing road caused by the project’s rebuilding and upgrading works
- Road encroachment due to soil from the new embankment under the project
- Access and safety
- Inadequate consultations
|
- Complaint received, 24 September 2021
- Complaint acknowledged and registered, 27 September 2021
- Eligibility (not eligible, complainants have yet to address problem with concerned ADB operations department), 20 October 2021
|
SPF-2021-09-01-0112 |
Pakistan: Central Asia Regional Economic Cooperation Corridor Development Investment Program-Tranche 1 |
- Land acquisition and compensation
|
- Complaint received, 7 July 2021
- Complaint acknowledged and registered, 8 July 2021
- Eligibility (not eligible, complainants have yet to address problem with concerned ADB operations department), 4 August 2021
|
SPF-2021-08-04-0111 |
Pakistan: Peshawar Sustainable Bus Rapid Transit Corridor Project |
- Compensation for the incurred business losses due to the delayed construction
|
- Complaint received, 6 July 2021
- Complaint acknowledged and registered, 7 July 2021
- Eligibility (not eligible, concerned ADB operations department is working with the project authorities to address the issues raised in the complaint), 3 August 2021
- Closed, 19 January 2022
|
SPF-2021-05-01-0108 |
Armenia: Sustainable Urban Development Investment Program – Tranche 2 |
- Dust pollution
- Damage to trees
|
- Complaint received, 8 March 2021
- Complaint acknowledged and registered, 9 March 2021
- Eligibility (not eligible, concerned ADB operations department is working with the complainants to resolve the complaint), 22 March 2021
- Closed, 13 July 2022
|
SPF-2021-02-02-0105 |
Pakistan: Jalalpur Irrigation Project |
- Land acquisition, valuation, and compensation
|
- Complaint received, 12 January 2021
- Complaint acknowledged and registered, 14 January 2021
- Eligibility (not eligible, concerned ADB operations department is working with the project authorities and complainants to resolve the complaint), 2 February 2021
- Closed, 25 April 2022
|
SPF-2021-01-01-0104 |
Pakistan: Punjab Intermediate Cities Improvement Investment Project |
- Land acquisition, valuation, and compensation
- Lack of meaningful consultation and participation
- Inadequate information dissemination
- Livelihood restoration
|
- Complaint received, 7 January 2021
- Complaint acknowledged and registered, 13 January 2021
- Eligibility (not eligible, concerned ADB operations department is working with the project authorities and complainants to resolve the complaint), 27 January 2021
- Closed, 2 June 2022
|
SPF-2020-09-03-0101 |
Pakistan: Peshawar Sustainable Bus Rapid Transit Corridor Project |
- Loss of business and livelihoods
- Devaluation of properties/shops
- Unsafe pedestrian road access
|
- Complaint received, 10 December 2020
- Complaint acknowledged and registered, 15 December 2020
- Eligibility (not eligible, concerned ADB operations department is working with the project authorities to address the issues raised in the complaint), 14 January 2021
- Closed, 19 January 2022
|
SPF-2020-07-01-0099 |
Pakistan: Khyber Pakhtunkhwa Provincial Roads Improvement Project |
- Loss of access to the shops due to the project resulting in reduced commercial activity
- Impact on livelihoods
|
- Complaint received, 21 October 2020
- Complaint acknowledged and registered, 22 October 2020
- Eligibility (not eligible, concerned ADB operations department is working with the project authorities and complainants to resolve the complaint), 9 November 2020
- Closed, 15 May 2022
|
SPF-2020-05-01-0097 |
Georgia: Natakhtari-Jinvali Road Project |
- Loss of agriculture production
- Impact on livelihoods and tourism
- Damage to the ecosystem
|
- Complaint received, 8 October 2020
- Complaint acknowledged and registered, 9 October 2020
- Eligibility (not eligible, the project is in the ADB pipeline but not yet processed for Management or Board consideration), 28 October 2020
|
SPF-2020-04-01-0096 |
Pakistan: Jalalpur Irrigation Project |
- Land acquisition and compensation
|
- Complaint received, 1 September 2020
- Complaint acknowledged and registered, 2 September 2020
- Eligibility (not eligible, complainants have yet to address problem with concerned operations department), 9 September 2020
|
SPF-2019-10-02-0090 |
Pakistan: MFF Power Transmission Enhancement Investment Program II - Tranche 3 |
|
- Complaint received, 29 August 2019
- Complaint acknowledged and registered, 25 September 2019
- Eligibility (not eligible, complainants not foreseen as project affected people), 25 September 2019
|
SPF-2019-08-02-0088 |
Pakistan: Peshawar Sustainable Bus Rapid Transit Corridor Project |
- Delay in compensation payments
|
- Complaint received, 8 July 2019
- Complaint acknowledged and registered, 9 July 2019
- Withdrawn prior to eligibility determination, 15 July 2019. Complainants are satisfied with the resolution of the project authorities and concerned ADB operations department on the issues.
|
SPF-2019-07-01-0087 |
Pakistan: MFF Power Transmission Enhancement Investment Program II - Tranche 3 |
- Lack of adequate consultation regarding project site selection leading to displacement of 120 poor farmer families.
|
- Complaint received, 19 June 2019
- Complaint acknowledged and registered, 20 June 2019
- Eligibility (eligible), 20 June 2019
|
SPF-2019-04-01-0084 |
Pakistan: Pehur High Level Canal Extension Project (formerly Khyber Pakhtunkawa Water Resources Project) |
- Reduced farm productivity and loss of income
|
- Complaint received, 13 March 2019
- Complaint acknowledged and registered, 13 March 2019
- Eligibility (eligible), 23 April 2019
|
SPF-2018-11-02-0080 |
Georgia: Batumi Bypass Road Project |
- Property valuation
- Business loss and compensation
|
- Complaint received, 2 October 2018
- Complaint acknowledged and registered, 3 October 2018
- Eligibility (eligible), 9 October 2018
- Final Report, 3 September 2019
|
SPF-2018-08-01-0077 |
Pakistan: Flood Emergency Reconstruction and Resilience Project |
- Substandard reconstruction of road
|
- Complaint received, 11 June 2018
- Complaint acknowledged and registered, 14 June 2018
- Eligibility (not eligible), 4 July 2018
- Closed, 17 March 2021
|
SPF-2018-07-01-0076 |
Pakistan: Peshawar Sustainable Bus Rapid Transit Corridor Project |
- Business loss/profit
- Compensation
|
- Complaint received, 10 May 2018
- Complaint acknowledged and registered, 15 May 2018
- Eligibility (not eligible), 4 June 2018
|
SPF-2018-06-01-0075 |
Pakistan: National Highway Network Development in Balochistan Project |
- Land ownership
- Compensation
|
- Complaint received, 6 April 2018
- Complaint acknowledged and registered, 11 April 2018
- Eligibility (eligible), 7 May 2018
|
SPF-2018-04-01-0073 |
Georgia: Adjaristsqali Hydropower Project |
- Impacts of the project on the natural and social environment of the village
- Village safety
|
- Complaint received, 8 March 2018
- Complaint acknowledged and registered, 8 March 2018
- Eligibility (eligible), 12 March 2018
- Closed, 7 December 2020
- European Bank for Reconstruction and Development Independent Project Accountability Mechanism Problem Solving Completion Report, October 2020
- International Finance Corporation and Multilateral Investment Guarantee Agency Compliance Advisor Ombudsman Dispute Resolution Conclusion Report, October 2020
|
SPF-2018-02-02-0071 |
Armenia: Sustainable Urban Development Investment Program - Tranche 1 |
- Impact of road construction to property and people’s safety
- Compensation
|
- Complaint received, 12 February 2018
- Complaint acknowledged and registered, 15 February 2018
- Eligibility (not eligible), 12 March 2018
- Closed, 1 September 2021
|
SPF-2018-01-01-0070 |
Kazakhstan: Akmola Electricity Distribution Network Modernization and Expansion Project |
- High cost of new equipment and connection fee to the grid network
|
- Complaint received, 15 January 2018
- Complaint acknowledged and registered, 15 January 2018
- Eligibility (not eligible), 9 February 2018
|
SPF-2017-10-01-0067 |
Armenia: Sustainable Urban Development Investment Program – Tranche 1
|
- Impact of road construction to property and people’s safety
- Compensation
|
- Complaint received, 5 September 2017
- Complaint acknowledged and registered, 6 September 2017
- Eligibility (eligible), 29 September 2017
- Final Report, 15 December 2017
|
SPF-2017-09-01-0066 |
Georgia: Batumi Bypass Road Project
|
- Property and land valuation
- Compensation
|
- Complaint received, 24 August 2017
- Complaint acknowledged and registered, 28 August 2017
- Eligibility (not eligible), 21 September 2017
- Closed, 2 March 2018
|
SPF-2017-06-05-0063 |
Georgia: MFF-Sustainable Urban Transport Investment Program - Tranche 3
|
- Loss of business
- Compensation
|
- Complaint received, 14 August 2017
- Complaint acknowledged and registered, 15 August 2017
- Eligibility determined (not eligible), 8 September 2017
|
SPF-2017-05-04-0062 |
Georgia: MFF-Sustainable Urban Transport Investment Program - Tranche 3
|
- Material harm due to road construction
- Health issues
|
- Complaint received, 10 July 2017
- Complaint acknowledged and registered, 10 July 2017
- Eligibility (not eligible), 7 August 2017
|
SPF-2017-03-03-0060 |
Georgia: MFF-Sustainable Urban Transport Investment Program - Tranche 3 (Section 2, Part B of the Tbilisi-Rustavi Urban Road Link)
|
- Evaluation of property
- Land acquisition and Compensation
|
- Complaint received, 10 April 2017
- Complaint acknowledged and registered, 11 April 2017
- Eligibility (not eligible), 8 May 2017
|
SPF-2016-05-02-0056 |
Georgia: MFF Sustainable Urban Transport Investment Program - Tranche 2 (3rd section of Tbilisi-Rustavi Road)
|
|
- Complaint received, 17 Nov 2016
- Complaint acknowledged and registered, 17 Nov 2016
- Eligibility (not eligible), 10 January 2017
|
SPF-2016-04-01-0055 |
Georgia: MFF Sustainable Urban Transport Investment Program - Tranche 2 (Section 3)
|
|
- Complaint received, 9 Nov 2016
- Complaint acknowledged and registered, 9 Nov 2016
- Eligibility (not eligible), 6 December 2016
|
SPF-2016-03-02-0054 |
Georgia: MFF Sustainable Urban Transport Investment - Program Tranche 3
|
|
- Complaint received, 27 May 2016
- Complaint acknowledged and registered, 30 May 2016
- Eligibility (not eligible), 1 Aug 2016
|
SPF-2016-02-01-0053 |
Georgia: MFF Sustainable Urban Transport Investment Program – Tranche 3 |
- Compensation and resettlement
|
- Complaint received, 28 Apr 2016
- Complaint acknowledged, 28 Apr 2016
- Complaint registered, 28 Apr 2016
- Eligibility determined (eligible), 20 May 2016
- Summary of the Review and Assessment Report, 28 Sep 2016
- Closed, 7 Aug 2017
- Issues raised under this complaint are similar to the complaint, on the same project, already dealt with by the Compliance Review Panel. Complaint to be consolidated, and issues raised which are noncompliance with ADB’s operational policies and procedures would thus need to be addressed by the Management as part of the remedial actions for the first complaint under compliance review.
|
SPF-2016-01-01-0052 |
Pakistan: MFF Power Distribution Enhancement Investment Program - Tranche 2 |
- Horizontal clearance for 132 Kv electric wire crossing properties and other structures
|
- Complaint received, 18 Mar 2016
- Complaint acknowledged, 21 Mar 2016
- Complaint registered, 21 Mar 2016
- Eligibility determined (not eligible, complainants have yet to address problem with concerned operations department), 11 Apr 2016
- Closed, 24 Mar 2021
|
SPF-2013-06-01-0047 |
Pakistan: Emergency Reconstruction Project |
- Quality of reconstruction works
|
- Complaint received, 9 Dec 2013
- Complaint acknowledged and registered, 9 Dec 2013
- Eligibility determined (not eligible, 30 Dec 2013)
- Closed, 5 May 2017
|
SPF-2013-05-02-0046 |
Armenia: Zvartnots Airport Expansion Project (Phase 2) |
- Resettlement
- Consultation
- Information
|
- Complaint received, 1 Aug 2013
- Complaint registered, 6 Aug 2013
- Eligibility determined (not eligible, Operations Department is addressing concerns), 7 Aug 2013
- Closed, 25 Oct 2016
|
SPF-2013-04-01-0045 |
Kyrgyz Republic: Loan 2755 (SF): CAREC Corridor 1 (Bishkek-Torugart Road) Project 3 |
- Environment
- Information Sharing
|
- Complaint received, 11 Jul 2013
- Complaint acknowledged and registered, 12 Jul 2013
- Eligibility determined (not eligible, Operations Department’s efforts are underway to implement OSPF's recommendations), 30 Jul 2013
- Closed, 7 Feb 2020
|
SPF-2013-03-01-0044 |
Armenia: Zvartnots Airport Expansion Project (Phase 2) |
- Resettlement
- Consultation
- Information
|
- Complaint received, 4 Jul 2013
- Complaint acknowledged and registered, 5 Jul 2013
- Eligibility determined (not eligible, Operations Department's efforts to address concerns are underway. OSPF's involvement would not be useful at this time), 23 Jul 2013
- Closed, 25 Oct 2016
|
SPF-2011-07-02-0039 |
Kazakhstan: CAREC Transport Corridor I Investment Program |
|
- Complaint received, 20 Dec 2011
- Complaint acknowledged and registered, 21 Dec 2011
- Eligibility Determined (not eligible, complainants have yet to address the problem with the concerned operations department), 4 Jan 2012
|
SPF-2011-04-01-0036 |
Pakistan: Proposed MFF National Trade Corridor Highway Investment Program - Hasanabdal-Havelian Section (Project 2) |
- Road alignment
- Land acquisition
|
- Complaint received, 6 Oct 2011
- Complaint acknowledged and registered, 11 Oct 2011
- Eligibility determined (not eligible, complainants have yet to address the problem with the concerned operations department), 28 Oct 2011
|
SPF-2010-07-01-0032 |
Georgia: Sustainable Urban Transport Investment Program |
|
- Complaint received, 27 Oct 2010
- Complaint acknowledged and registered, 5 Nov 2010
- Eligibility determined, (not eligible, complainants have yet to address the problem with the concerned operations department), 19 Nov 2010
|
SPF-2010-06-01-0031 |
Kyrgyz Republic: Southern Agriculture Area Development Project |
- Information
- Consultation/Participation
|
- Complaint received, 28 Sep 2010
- Complaint acknowledged and registered, 5 Oct 2010
- Eligibility determined (not eligible; there was no direct harm, as the project was not implemented), 21 Oct 2010
|
SPF-2010-05-01-0030 |
Kyrgyz Republic: Technical Assistance: Regional Economic Integration in Central Asia – Stocktaking and Experience Sharing |
|
- Complaint received, 27 Sep 2010
- Complaint acknowledged and registered, 29 Sep 2010
- Eligibility determined (not eligible; procurement related matters are not eligible for complaints), 29 Sep 2010
|
SPF-2010-04-01-0029 |
Kyrgyz Republic: CAREC Transport Corridor 1 (Bishkek-Torugart Road) Project 1 |
|
- Complaint received, 7 Sep 2010
- Complaint acknowledged and registered, 22 Sep 2010
- Eligibility determined (eligible), 12 Nov 2010
- Review and Assessment Report (RAR), 14 Dec 2010
- Agreed Course of Action, 20 Apr 2011
- Final Report, 2 Nov 2011
|
SPF-2010-02-01-0027 |
Tajikistan: Education Sector Reform Project |
- Information
- Consultation
- School Reconstruction
|
- Complaint received, 5 Aug 2010
- Complaint acknowledged and registered, 6 Aug 2010
- Eligibility determined (eligible), 1 Sep 2010
- Review and Assessment Report (not public), 27 Oct 2010
- Final Report, 26 Oct 2011
|
SPF-2010-01-01-0026 |
Kazakhstan: CAREC Transport Corridor I Investment Program |
- Bus Stop
- Underpass for agricultural machinery
|
- Complaint received, 4 Jun 2010
- Complaint acknowledged and registered, 14 Jun 2010
- Eligibility determined (not eligible, complainants have yet to address the problem with concerned operations department), 26 Jul 2010
|
SPF-2009-12-01-0024 |
Kazakhstan: CAREC Transport Corridor I Investment Program |
- Information
- Participation
- Cattle passes
- Underpass for agricultural machinery
|
- Complaint received, 5 Nov 2009
- Complaint acknowledged and registered, 10 Nov 2009
- Eligibility determined (eligible), 3 Dec 2009
- Review and Assessment Report (RAR), 8 Feb 2010
- Agreed Course of Action, 2 Mar 2010
- Monitoring Report, Mar 2011
- Comments on Monitoring Report
- Final Report, Sep 2012
|
SPF-2009-10-01-0022 |
Azerbaijan: Multitranche Financing Facility Road Network Development Program |
|
- Complaint received, 3 Sep 2009
- Complaint acknowledged and registered, 4 Sep 2009
- Eligibility determined (not eligible, complainants have yet to address the problem with the concerned operations department), 30 Oct 2009
|
SPF-2009-09-01-0021 |
Azerbaijan: East-West Highway Improvement Project |
- Consultation
- Information
- Resettlement
|
- Complaint received, 2 Sep 2009
- Complaint acknowledged and registered, 3 Sep 2009
- Eligibility determined (not eligible, complainants will not be directly affected by the ADB-assisted project and complaint has not yet been raised with the concerned operations department), 30 Oct 2009
|
SPF-2009-08-02-0020 |
Pakistan: Rawalpindi Environmental Improvement Project (Water Supply Component) |
|
- Complaint received, 13 Aug 2009
- Complaint acknowledged and registered, 13 Aug 2009
- Eligibility determined (not eligible; complainants are not materially and adversely affected by the project), 25 Aug 2009
|
SPF-2009-07-01-0019 |
Pakistan: National Trade Corridor Highway Investment Program |
- Compensation
- Land Acquisition
|
- Complaint received, 01 Jul 2009
- Complaint acknowledged and registered, 01 Jul 2009
- Eligibility determined (not eligible; complainants have yet to address problem to the Operations Department), 11 Jul 2009
|
SPF-2009-06-01-0018 |
Pakistan: Rawalpindi Environmental Improvement Project (Sewage Treatment Plant Component) |
- Land Acquisition
- Compensation
|
- Complaint received, 28 May 2009
- Complaint acknowledged, 1 Jun 2009
- Complaint registered, 4 Jun 2009
- Eligibility determined (eligible), 18 Jun 2009
- Review and Assessment Report, 24 Jul 2009
- Final Report, 2 Nov 2010
|
SPF-2009-05-01-0017 |
Pakistan: National Trade Corridor Highway Investment Program |
|
- Complaint received, 24 Apr 2009
- Complaint acknowledged and registered, 30 Apr 2009
- Eligibility determined (not eligible; Operations Department's efforts to address concerns are underway. OSPF's involvement would not be useful at this time), 26 May 2009
|
SPF-2009-04-01-0016 |
Pakistan: North-West Frontier Province Road Development Sector and Subregional Connectivity |
|
- Complaint received, 9 Apr 2009
- Complaint acknowledged, 13 Apr 2009
- Complaint registered, 30 Apr 2009
- Eligibility determined (not eligible; complainants never addressed problem to Operations Department), 30 Apr 2009
|
SPF-2009-02-01-0014 |
Pakistan: Southern Punjab Basic Urban Services Project |
|
- Complaint received, 27 Feb 2009
- Complaint acknowledged, 18 Mar 2009
- Complaint registered, 30 Apr 2009
- Eligibility determined (eligible), 25 May 2009
- Review and Assessment Report (RAR), 2 Jul 2009
- Final Report (not public), 23 May 2012
|
SPF-2006-04-01-0008 |
Pakistan: National Highway Development Sector Investment Program |
- Land acquisition and compensation
- Resettlement
- Information
|
- Complaint received, 9 Sep 2006
- Complaint acknowledged, 12 Sep 2006
- Translation, establishing contact and fielding a pre-eligibility inquiry, Oct-Dec 2006
- Read the Pre-Eligibility Screening Report, 31 Dec 2006
- Complaint registered, 10 Jan 2007
- Eligibility determined (eligible), 29 Jan 2007
- Review and Assessment report (RAR), 12 Mar 2007
- Agreed Course of Action, 17 May 2007
- Monitoring Report, Jun 2008
- Monitoring Report, Jun 2009
- SPF's Final Report, 19 Mar 2010
|
SPF-2006-01-01-0005 |
Pakistan: Chasma Right Bank Irrigation Project-Stage III |
- Distributary link
- Flooding
|
- Complaint received, 14 Dec 2005
- Complaint acknowledged and registered, 15 Dec 2005
- SPF initiatives in establishing contact with complainants, translations, and fielding a pre-eligibility inquiry, Jan-Aug 2006.
- Read the Pre-Eligibility Screening Report, 31 Aug 2006.
- Eligibility determined (not eligible; issues initially raised with SPF have been addressed by government. Operations Department followed-up on new issues.), 05 Dec 2006
|